MSMS Football/Track Complex |
|
|
¨
Sheet rock is complete at the
concession stand/rest rooms
and ticket booth
.
|
|
|
¨
Metal siding is complete
. |
|
|
¨
Football goals are ordered
. |
|
|
¨
The scoreboard has been moved. |
|
| |
|
|
Complete High School
Maize |
|
|
¨
Equipment and supplies were
moved from MMS building 2 on
August 16, 18 and 19. Students
and staff were able to occupy
the building on time. |
|
|
¨
Bids for the irrigation system
are being collected |
|
|
¨
Moisture levels of the
concrete floors are being
monitored, and the floor time
will be installed when
appropriate levels are reached
. |
|
|
¨
Tree planting is near
completion
. |
|
|
|
| |
|
|
MHS Welcome Center/Police
Building |
|
|
¨
The building is complete. |
|
| |
|
|
Remodel Old Middle School
|
|
|
¨
Demolition is complete |
|
|
¨
Bricklayers are closing in
window and door openings. |
|
| |
|
|
MHS Reflection Area
|
|
|
¨
Grass has been seeded
. |
|
|
¨
Concrete bids are being
collected
. |